AEMO hits back at VEPC criticism

The Australian Energy Market Operator (AEMO) has called criticisms of their WRL-VNI West project made by the Victorian Energy Policy Centre (VEPC) “contrary to both government policy and numerous independent economic analyses”.

AEMO’s WRL-VNI is a controversial proposed renewable energy transmission project, which would require land acquisition to create an easement for transmission towers and lines across western Victoria, including through Melton and Moorabool.

Star Weekly reported that the VEPC released a damning report of the project, academics behind the report calling the project “biggest mistake in transmission planning in living memory”.

In a statement on April 26 AEMO’s System Design executive general manager Merryn York hit back at a number of VEPC claims, including that it would be easier to upgrade existing transmission lines in Gippsland and Latrobe Valley and that the project could triple transmission charges.

Ms York said that “detailed engineering and economic analysis” demonstrates a need to both harness the existing transmission and build new infrastructure, and that AEMO estimates a 25 per cent increase in transmission costs for Victorian consumers.

Former member of the National Electricity Market’s reliability panel and electrical engineering professor Simon Bartlett, who co authored the VEPC report said AEMO has not allowed for “realistic ongoing costs of VNI West and WRL”.

“With an existing transmission capacity of 9,450MW that can be used immediately and easily expanded to 17,600MW [the existing Gippsland transmission network] is the quickest, cheapest and most reliable way for Victoria to make substantial progress in the transition from coal to renewables,” he said.

Another point of criticism from VEPC was state-wide blackouts caused by natural disasters collapsing or causing electrical faults on any one of the 1,500 transmission towers on WRL/VNI West, which Ms York said this is “not supported by any evidence”.

Professor Bartlett pointed to examples where destructive winds collapsed six 500kV transmission towers, and fires have tripped or forced out of service interconnectors in Victoria, leading to widespread blackouts and long repair times.

AEMO chief executive Daniel Westerman said the urgent need for new transmission to bridge the gap left by the rapid exit of coal-fired generation was not unique to Australia.

“Governments and system planners worldwide are wrestling with the urgent need to build new transmission to guarantee the safe, secure and reliable supply of basic services to towns and cities,” he said.

Digital Editions


More News

  • Cricket star on the rise

    Cricket star on the rise

    “I love the beauty of playing cricket,” reflects this month’s Don Deeble Sports Star award winner. Jasmine Kamboj was only six when she became restless watching her older brother and…

  • New MICA paramedics to strengthen emergency care

    New MICA paramedics to strengthen emergency care

    Purchase this photo from Pic Store: 303384 “Our MICA paramedics are some of the world’s best,” said Minister for Ambulance Services Mary-Anne Thomas, as she welcomed the latest cohort of…

  • Cleopatra performance showcases local talent

    Cleopatra performance showcases local talent

    A powerful new ballet is set to captivate audiences in Caroline Springs this March, as a cast of passionate adult performers present Cleopatra, The Last Pharaoh at the Catholic Regional…

  • Cobblebank hub needs a name

    Cobblebank hub needs a name

    Purchase this photo from Pic Store: 260628 Melton council is inviting residents to help choose the name of a new five-level community services building in Cobblebank, with six shortlisted options…

  • Locals scrub up over summer clean-up

    Locals scrub up over summer clean-up

    Melton’s rubbish collectors have had a busy start to the year, with locals taking full advantage of their free hard waste collections and drop-offs to dispose of unwanted items the…

  • Car theft crackdown

    Car theft crackdown

    Purchase this photo from Pic Store: 206998 More than 100 charges have been laid over the course of four nights as police crack down on car thefts in Melbourne’s west.…

  • Council investigates traffic issues

    Council investigates traffic issues

    Purchase this photo from Pic Store: 260628 Melton council has moved on tackling traffic issues raised by residents of Deanside Village estate. At its 23 February meeting, council resolved to…

  • Severe thunderstorm warning issued

    Severe thunderstorm warning issued

    Purchase this photo from Pic Store: 253047 A severe thuderstorm warning and shelter indoors now alert has been issued for suburbs around Melbourne’s north-west. Residents in Sunbury, Sydenham, St Albans,…

  • Residents to name ‘biggest ever’ Melton build

    Residents to name ‘biggest ever’ Melton build

    Purchase this photo from Pic Store: 260628 Melton council is calling on locals to help shape the identity of Fraser Rise’s upcoming aquatic centre, Melton’s ‘biggest ever’ capital project. Community…

  • Patient play pays off for Svanosio

    Patient play pays off for Svanosio

    Chris Svanosio finished the meeting with a rush, landing the last two winners to bring up a training double at Melton on Saturday night. Ultra-consistent trotter Kyvalley Maven found his…